Transmission Pipeline System Replacement

Replace 32 miles of aging 20″ and 26″ with new 36″ pipe co-located with an existing 30″ pipe to remain in service. Upgrade and tie into existing compressor stations.

  • Location: Kansas
  • Total Install Cost Estimating and Scope Development FERC 7 ( c ) filing
  • Pipeline and compression system evaluation
  • Replace and re-connect multiple laterals
  • Redesign and upgrade both storage field compressor stations
  • Completion Year: 2020
Challenges
  • Complex system evaluation
  • Various types of compression to analyze
  • Multiple pipeline MAOPs

Related Projects